Site meeting
Site meetings are an important part of the successful management of construction projects. Regular site meetings between the different stakeholders on a project can help facilitate better communication and a shared sense of purpose making it more likely that the project is completed successfully. Project failures are often attributed to inadequate management, with a key factor being a lack of proper communication.
Meetings should be regular and formerly scheduled, perhaps on a weekly or monthly basis depending on the parties involved, although the size and complexity of the project may necessitate a more regular schedule. They are used as a means of reporting progress, enabling discussion of any problems or issues, and allowing the proposal of solutions. They provide a good opportunity for two-way discussions of any issues that have arisen or that are anticipated.
Holding meetings on site enables the stakeholders to see progress for themselves (rather than relying on a report for another party), and to look at problem areas, discuss quality issues, assess mock-ups, and so on.
Construction progress meetings are a specific sort of site meeting during which the contract administrator receives progress reports from the contractor and consultant team, cost reports from the cost consultant and other more specific information such as sub-contractor reports, progress photos, and so on.
In order to be able to provide the correct information at construction progress meetings, the contractor may previously hold a progress meeting with sub-contractors sometimes called a production meeting.
Meeting minutes should be prepared, with a requirement that any disagreement with the items recorded in the minutes is raised within a pre-defined period (perhaps one week). Progress meetings may also result in the preparation of a construction progress report for the client.
On construction management projects, the construction manager holds regular construction progress meetings with trade contractors to discuss on and off-site progress against the programme and to co-ordinate the release of information. It may sometimes be appropriate for these meetings to take place at the trade contractor's premises. On large projects the construction manager may hold a daily logistic meeting on site with trade contractor foremen to organise, schedule and co-ordinate on-site shared services such as deliveries and off-loading, hoists and cranage, scaffolding, safety issues, rubbish clearance etc.
Similar meetings may be held on management contract projects between the management contractor and the works contractors.
Other meetings held on site might include safety briefings and toolbox talks which are held to ensure that workers properly consider health and safety issues on site.
[edit] Related articles on Designing Buildings
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Comments